Minutes of the
regular meeting of the Georgetown Township Planning Commission, held Wednesday,
October 18, 2006
Meeting called to order by
Chairman Honderd at 7:30 p.m.
Present: Honderd, Poskey, DeGood, South,
Stasiak, Huizinga
Absent: Pearson
#061018-01 - Agenda for October 18, 2006
Moved by
DeGood, seconded by Stasiak, to approve the agenda for October 18, 2006, as
presented.
MOTION
CARRIED.
#061018-02 - Minutes of
the October 4, 2006 regular meeting
Moved
by Stasiak, seconded by DeGood, to approve the minutes of the October 4, 2006 meeting,
as submitted.
MOTION
CARRIED.
#061018-03 - Unfinished Business Preliminary Plat of Crosswinds
The
zoning administrator stated that the issue of dry sewer for the plat would have
to be reversed by the Township Board in order for dry sewer to be installed
since the Board already denied the request.
The consensus of the Planning Commission was to leave the item tabled to
give the applicant time to work out the remaining issues.
#061018-04 - Site Plan (ST0609) Campus
View Townhouses (revised)-
Doug
Stalsonburg, Exxel Engineering, represented the applicant and presented the
request.
The
zoning administrator presented a review as follows.
No
public hearing is required for a site plan.
At the July 20, 2005 Planning Commission meeting, the site plan was
approved for these phases of townhouses.
SUMMARY
The request is to approve changes to a previously
approved site plan that have been determined to not meet the criteria of a
minor change under Sec. 19.8 since buildings 32 and 33 would be moved by more
than 10 feet. Since this is a revision to
a previously approved plan, the proposed conditions could be attached to ensure
compliance with the ordinance.
The revisions include the following:
a. The previous plan showed phase six encompassing
buildings 20 to 43. The revised plan
shows phase six as encompassing buildings 20 to 26, phase seven as encompassing
buildings 27 to 33, phase seven as encompassing buildings 27 to 33 and phase
eight as encompassing buildings 34 to 43.
b. The total number of units has been reduced from 316 to
314. The density is 7.73 units per acre
which is well within the fifteen units per acre permitted in Chapter 24
footnote (i). Buildings 30, 32 and 33
have increased in square footage.
c. Buildings 32 and 33 have been reoriented.
Following is the documentation showing compliance
with Ordinance requirements.
|
I D number |
ST0609 |
|
|
|
Date |
10/11/06 |
|
|
|
Name |
Campus View
Townhouses |
|
|
|
|
|
||
|
Address |
10081 42nd
Ave. |
|
|
|
|
|
|
|
|
Use |
11.2(B)
Townhouses |
|
SUP
required |
no |
||||
|
|
|
|
|
|
|
|
|
|
|
REQUIREMENT |
|
|
|
|
|
PROVIDED |
Needs or Comments |
|
|
Date, north
arrow, scale |
|
|
|
|
X |
|
||
|
Name,
address of preparer |
|
|
|
|
X |
|
||
|
Name,
address of property owner or petitioner |
|
|
X |
|
||||
|
Location
sketch |
|
|
|
|
|
X |
|
|
|
Legal
description |
|
|
|
|
|
X |
|
|
|
Size in
acres of the property |
|
|
|
|
X |
|
||
|
Property
lines and required setbacks shown and dimensioned |
|
X |
|
|||||
|
Location of
existing structures, drives, parking areas within 100 ft of boundary |
X |
|
||||||
|
Location
and dimensions of existing and proposed structures |
|
X |
|
|||||
|
Location of
existing and proposed drives (dimensions and radii), circulation |
X |
a.
condition |
||||||
|
Sidewalks,
non-motorized paths-select streets, accel, decel lanes |
|
|
|
|
X |
a.
condition |
||
|
Signs,
exterior lighting |
|
|
|
|
|
X |
a.
condition |
|
|
Curbing,
parking areas, dimensions of typical space, number of parking spaces |
X |
|
||||||
|
Calculations
of parking spaces, unloading areas |
|
|
X |
|
||||
|
Location,
pavement width, ROW of all abutting roads, easements |
|
X |
|
|||||
|
Existing
zoning, and zoning and use of abutting property |
|
|
X |
|
||||
|
Location of
existing vegetation-parkway association |
|
|
|
|
NA |
|
||
|
Location,
type, size of proposed landscaping, streetscape, greenbelt |
X |
a.
condition |
||||||
|
Location,
height, type of existing and proposed fences and walls |
|
X |
|
|||||
|
Size,
location of proposed, existing utilities, connections to water/sewer |
X |
|
||||||
|
Location,
size of surface water drainage facilities |
|
|
X |
b. permit needed |
||||
|
Existing,
proposed topo contours, max 5 ft intervals |
|
|
X |
|
||||
|
Rec/common
areas, floodplain areas |
|
|
|
X |
|
|||
|
Residential
development extra requirements-attached garages |
|
X |
a.
condition |
|||||
Notes:
a. Conditions
of approval should be added to ensure compliance with the ordinance (since this
was a previously approved site plan) as follows: for the buildings to be
constructed as per the previously submitted elevations (including garages); a
landscape plan should be resubmitted (showing compliance with the ordinance-one
had been previously submitted); the sign must be at least 60 feet from the
centerline of 42nd Ave. and must meet ordinance requirements; site
lighting should be downward directing; the driveway to 42nd Ave.,
sidewalks and landscaping should be provided at the time of construction of any
buildings 34 to 42;
b. A
Storm Water Drain Permit must be provided along with the building permit
application.
Landscape Preservation. NA
Relation of Buildings to Environment.
Elevations
provided with previous application and approval.
Lighting
details provided and must be downward directing.
Landscaping
meets the ordinance requirements and a new plan should be provided.
Drives, Parking, and Circulation.
The drive to 42nd
Ave., sidewalks and landscaping should be provided along 42nd Ave.
with the
construction of any buildings 34
to 42.
Surface
Water Drainage
The
Drain Commission will review the plans and an approval is required from them at
the time of building permit submittal.
Utility
Service
Shown and
will be reviewed by the appropriate agencies.
The chairman opened the floor to public comments. No one was present to comment on this
request.
Doug Stalsonburg stated that the Drain Commissioner
had directed how storm water is to be managed on the site.
The zoning administrator stated that a Storm Water
Drain Permit would be required from the County approving the storm water
management on the site at the time a building permit application is submitted.
Moved
by Stasiak, seconded by DeGood, to approve the site plan dated revised Oct. 3,
2006 based on
the findings that the plan meets applicable ordinance requirements with the following conditions:
a.
The buildings be
constructed as per the elevations (which show attached garages) that were
previously approved with the site plan on July 20, 2005;
b. A landscape plan and legend be provided at the time a
building permit application is submitted to the Township that meets ordinance
requirements for number, size and type (frontage is 708 feet and 29 trees must
be provided with a maximum of 9 evergreen trees) (can be a copy of the one
previously approved on July 20, 2005);
c. The sign must meet ordinance requirements and be
located at least 60 feet from the centerline of 42nd Ave.;
d. Site lighting must be downward directing and shall
deflect away from adjacent residential structures;
e. The driveway to 42nd Ave., sidewalk
adjacent to 42nd Ave., and landscaping is provided at the time of
construction of any buildings from 34 to 43;
f. A Storm Water Drain Permit is provided at the time a
building permit application is submitted to the Township.
MOTION
CARRIED.
#061018-05 – Adjournment
The
chairman adjourned the meeting at 7:40 p.m.