2006 March Report
DPW Department
- The Water/Sewer Township Specification Book has
been completed in its updates and is now on line at the township
website. Per comments by various
engineers and contractors, it is being used already.
- The new GT9 Meter/Booster Station is now in the
construction phase. Most of the
underground piping is in place and the foundation is scheduled to be
poured the week of April 3 through 7.
Construction is scheduled to be complete by the end of May.
- The new 2006 water and sewer pickup truck has not
arrived as yet, but is expected any time.
- GT4 Sunningdale Booster Station has had a
frequency drive installed on the pump motors. The goals are:
- increase pump efficiency
- decrease wear on motor and increase motor life
- decrease electric usage
- The meter at GT2 has been removed for
recalibration and any repairs if necessary. This will take a couple of weeks to
discover the cost and best direction to proceed.
- The Distribution System and Collection System
Maps are being updated by Prein & Newhof Engineers. The first draft of the Collection System
is in the office and is a great improvement. We are looking forward to the final
product.
- It looks like the construction season will be
greatly reduced from years past due to the housing market. However, many other projects are being
pursued and hope to be completed this year. Many of these projects were presented in
February’s report.
- At the year end tally we now have 137.52 miles of
sewermain in the ground. We also
have 237.77 miles of watermain in the ground.
- During the month of March we had:
1
hydrant hit due to an auto accident
1
watermain hit by Consumers Energy
1
watermain break
2
water service leaks
124 new homes under construction
15 new water meters installed
18 new sewer connections
57 final readings of water meters for home
sales
Respectfully submitted
Denny Bishop