2006 OCTOBER REPORT
DPW DEPARTMENT
- The
Sewer Televising for 2006 is complete with several problems which were
identified and all have been addressed.
- The
Air Release Program is being readdressed and changed to become more test
friendly.
- After
many weeks of Maplewood Park
being closed last summer, some progress is being made into pinpointing the
problem of e-coli bacteria in the lake.
We will continue to correct this problem for next year and the
years to come.
- The
on/off ramp is going to impact the water and sewer system to come
extent. Various meetings have been
attended to seek to correct these situations. Prein and Newhoff engineering firm is
being retained by Ottawa County
to review the issue with the sewer and Williams and Works was retained by
MDOT to address the issue with the water system.
- 68
new homes under construction
- 11
new meters installed
- 13
new sewer connections
- 57
final readings of water meters for home sales
- 15
water service repairs
Respectfully Submitted
Denny Bishop
DPW Director