Hello, everyone—

 

We thought you might like to see how the big project is coming along.  Attached are a couple of aerial photos of the project that were taken this past week.  The first one is taken looking south; the second is looking westerly toward Lake Michigan.

 

To date, the Contractor (Granger Construction) has poured about 9000 cubic yards of concrete.  There are only about 16,000 more to go….

 

To date, the Contractor has been paid $11,286,172.97.  This equates to about 16% completion.

 

Joe Stapf, P.E.

Director of Utilities